Present: |
Chair: | D. Frisch | City of Courtenay |
Vice-Chair: | W. Morin | City of Courtenay |
Members: | B. Wells | City of Courtenay |
| M. Swift | Town of Comox |
| K. Grant | Town of Comox |
| D. Arbour | Baynes Sound-Denman/Hornby Islands (Area A) |
| A. Hamir | Lazo North (Area 'B') |
Alt. Members: | M. McCollum | City of Courtenay |
| C. Scoville | Puntledge/Black Creek (Area C) |
Non-voting Members: | D. Allen | City of Courtenay Administrator |
| R. O’Grady | City of Courtenay |
| S. Ashfield | Town of Comox Engineer |
| R. Dyson | Chief Administrative Officer |
| K. La Rose | Acting General Manager of Engineering Services |
|
|
Staff: | B. Dunlop | Corporate Financial Officer | | J. Martens | Manager of Legislative Services |
| L. Dennis | Legislative Services Assistant |
|
|
|
|
|
|
| | | |
RECOGNITION OF TRADITIONAL TERRITORIES | |
The Chair acknowledged that the meeting was being held on the unceded traditional territory of the K’ómoks First Nation. |
  |
|
MANAGEMENT REPORT: | |
B. Wells/A. Hamir: THAT the Comox Valley Water Committee management report dated August 2019 be received. [Item] |
  | Carried |
|
REPORTS: | |
BULK WATER STANDPIPE UPGRADES |
  |
|
B. Wells/A. Hamir: THAT the report dated August 7, 2019 regarding a business case for upgrades to the Comox Valley Water System bulk water standpipe be received. [Item] |
  | Carried |
|
K. La Rose, Acting General Manager of Engineering Services, presented an overview of the staff report regarding a business case for upgrades to the Comox Valley Water System bulk water standpipe. [Item] |
  |
|
K. Grant/M. Swift: THAT the 2019-2023 financial plan and capital expenditures program for the Comox Valley Water Supply System Service, function 300, be amended to increase water infrastructure expenses in 2019 by $120,000 for upgrades to the bulk water standpipe located at 4795 Headquarters Road, to be funded by a contribution from capital works reserve #838. |
  | Carried |
|
B. Wells/K. Grant: THAT the ‘other than local government’ bulk water rate as outlined within Schedule A of Bylaw No. 190 being the “Comox Valley Water Supply System Bulk Water Rates, Bylaw No. 190, 2011” be amended from $1.42 per cubic meter to $3.91 per cubic meter to reflect capital, operating and administration costs associated with operation of the standpipe. |
  | Carried |
|
COMOX VALLEY WATER SUPPLY SYSTEM CONSUMPTION REPORT – QUARTERLY |
  |
|
K. Grant/A. Hamir: THAT the Comox Valley water supply system consumption report to June 30, 2019 be received. [Item] |
  | Carried |
|
TERMINATION: | |
K. Grant/A. Hamir: THAT the meeting terminate. |
  | Carried |
|
Time: 3:30 pm. |
  |
|
| Confirmed by:
____________________________________ David Frisch Chair |
| Certified Correct:
____________________________________ Jake Martens Manager of Legislative Services |
| Recorded By:
____________________________________ Lisa Dennis Legislative Services Assistant
These minutes were received by the Comox Valley Regional District board on the _________ day of _______, 20___. |